Development

Montrose City Mega Development

Project Location

Co-ordinates on the development are as follows; GPS: -26.231834, 27.643352

Project Description

It is a mixed integrated housing development from low cost, affordable and upper market residential units situated in the West Rand Region of Gauteng within Randfontein. It consists of 5 602 and 8 190 mixed use residential units on Phase 1 and 2 respectively. Montrose City Mega Development has a public and private participation which will yield schools, private and public hospitals, college/satellite university, government complex, theme parks, commercial agriculture, retail, commercial office parks, light and heavy industrial development and other public amenities which will yield a lot of economic opportunities and social integration.

The Montrose City Mega Development within there is a Middelvlei Station that we ae reviving that will add to the economic boost of the region and directly linking the Montrose City Mega Development with the entire West Rand Region as well as the entire Gauteng City Region. The Middelveli Station is part of the integrated transportation system that synchronizes buses, taxis and passenger train. It will be the economical hub of Montrose City Mega Development. Montrose city is a smart city that will have broadband connection throughout the development.

Property / Land Description

  • Portion 80 (Portion of Portion 6) of the Farm Middelvlei No. 255 IQ, Randfontein Gauteng, held under title deed T40699/2012 and measuring approximately 106.4916ha in extent; and
  • Portion 81 (Portion of Portion 6) of the Farm Middelvlei No. 255 IQ, Randfontein Gauteng held under title deed T40699/2012 and measuring approximately 24,4813ha in extent; and
  • The Remainder of Portion 6 of the Farm Middelvlei 255, Registration Division I.Q., Province of Gauteng, measuring 387.7624 (three eight seven comma seven six two four) hectares and held by Deed of Transfer number T19133/1973”;

Housing Brochure

Development Status

  • ROD
  • Traffic impact study
  • Geotechnical Investigation and Assessment report
  • Land Surveying
  • Occupational Health and Safety
  • Communication, Marketing and Social facilitation
  • Quantity surveyor
    • Stage 1 – 4 (100%) complete
  • Architecture
    • Stage 1 – 4 (100%)
  • Engineers
    • Stage 1 – 4 (100 % Complete)
  • Montrose Ext 1 Township Approval (Phase 2)
    • Layout plan 100 % complete
    • To be submitted in April 2017
    • Estimated full township approval date 30th November 2017
  • Environmental Impact Analysis
    • 35 % EIA Studies complete
    • Estimated completion and ROD Approval date 30th October 2017
  • Traffic Impact Study
    • 35 % complete
    • Estimated completion date 30th June 2017
  • Geotechnical Investigation & Assessment Report
    • 40 % complete
    • Estimated completion date 30th June 2017
  • Land Surveying
    • 25 % complete
    • Estimated completion date 30th June 2017
  • Occupational Health & Safety
    • Estimated design resume date is 30th November 2017
    • Estimated Completion date 28th February 2018
  • Quantity Surveyor
    • Estimated design resume date is 1st January 2018
    • Estimated Completion date 28th February 2018
  • Communication, Marketing, & Social Facilitation
    • Communication and marketing 40 % complete and estimated completion date is 30th June 2017
    • Most Social facilitation to be done during construction period
  • Architecture
    • Estimated design resume date is 30th November 2017
    • Estimated Completion date 28th February 2018
  • Engineers
    • Estimated design resume date is 30th November 2017
    • Estimated Completion date 28th February 2018
Development 90%
Design 80%
Marketing 70%